Let Natural Gas Benefit Thousands of Households as Soon as possible The East Branch Trunk Line Project of the Second West Line is Pushing Forward at Full Speed
After 22 days of struggle, at 16: 00 on November 25, the welding of the last nozzle of the river bottom pipeline
Release time:
2011-12-15
Source:
Jinjiang Crossing: Tunnel River Bottom Project Victory
After 22 days of struggle, at 16: 00 on November 25, the welding of the last nozzle of the river bottom pipeline of the Jinjiang crossing project tunnel in the eastern section of the west second line was completed. At 18: 30, the 535-meter-long pipeline was completely crossed and the tunnel river bottom project was successful.
Jinjiang Crossing Project is located in Gao'an City, Jiangxi Province, and is one of the control projects of the West Second Line Pipeline Project. Due to the small cross-section of pipe jacking through the tunnel, the operating space at the bottom of the well is limited, and the installation of pipes with a pipe diameter of 1219mm is difficult. The Project Department of Pipeline No. 4 Company closely cooperates with the Project Department of China Railway 16th Bureau, and adopts the forward traction method to complete the crossing of the supervisor.
Due to the tight construction period, the project department of the fourth pipeline company will arrange two construction units to carry out uninterrupted construction day and night, and will start to install the S-type return leveling pipeline in the starting well and the receiving well in the near future.
Qiantang River Shield: Pipeline Pressure Test Completed
On November 24, the pipeline pressure test and deep water sweeping of the Qiantang River Shield Project, a controlling project of the Shanghai branch trunk line in the eastern section of the Second West-East Gas Pipeline, were completed.
The total length of the Qiantang River shield project on the West Second Line is 2900 meters, the design pressure of the pipeline is 10 MPa, and the pipe diameter is 1016mm. This project is the longest small section and long distance shield tunnel in China.
In order to solve the problem of communication blind spots in the tunnel, the scientific research personnel of the Pipeline Bureau launched technical research, systematically solved the problems of wireless communication inside and outside the shield tunnel, and rectified them item by item. After nearly a month of on-site installation and commissioning, the wireless communication project inside and outside the shield tunnel was successfully tested in the Qiantang River shield, filling the gap in the field of wireless communication in the shield tunnel of the pipeline bureau. This is the first successful implementation of small cross-section, long-distance pipeline shield tunnel wireless communication project in China.
During the construction of the project, due to the narrow space in the tunnel and the inability of large-scale equipment to enter, the Qiantang River Shield Installation Project Department continued to innovate technology and transform equipment, and solved a number of problems. The staff overcame the difficulties of humidity and sultry heat in the tunnel, carefully organized, rationally deployed, reorganized the original construction team, and implemented uninterrupted construction throughout the day, which improved work efficiency. (Correspondent Song Yang)
Nanning Branch Trunk Line: Air Dragon Crossing "quicksand swamp"
Before arriving at the construction site of the Nanning branch trunk line project of the fifth pipeline company, the reporter heard that the pipeline construction in Zhaoqing, Guangdong and Wuzhou, Guangxi was extremely difficult. In early November, the reporter braved continuous rain and came here along the pipeline.
The areas along the Nanning branch trunk line have a lot of people and little land, and every inch of land is worth every inch of money. The second, third and fourth bid sections of the Nanning branch trunk line constructed by the Fifth Pipeline Company pass through Zhaoqing, Guangdong and Wuzhou, Guangxi, with a total length of 289.5 kilometers. The construction operation area is mainly hills, low mountains, inter-hill valleys and inter-mountain plains, with rivers, fish ponds and paddy fields intersecting along the line. In the 170-meter-long operation zone, more than 30 households are involved in ploughing fields.
In mid-April this year, as soon as the Nanning branch trunk line project started, the employees of the Nanning branch trunk line project department of the fifth pipeline company made difficulties.
Local complex geological conditions is a major problem faced by the construction. The staff of the project department said that this was something that had never been encountered in previous construction.
The geological conditions in the mountains and valleys are bad, and the construction work surface is narrow. Under the humus soil with a depth of 200mm to 300mm, there is bottomless quicksand, like a swamp. Under normal circumstances, let alone heavy equipment, people will "struggle deeper and deeper" when they get stuck ". The four welding units that first entered the construction of Nanning branch trunk line all had the experience of equipment falling into quicksand. An excavator with CPP519 unit construction, even in the case of bedding steel plate, can be swallowed by the "quicksand swamp. It took the project department 7 days to rescue the equipment by all means.
The local abundant rain and high temperature weather also brought great difficulties to the construction. The local climate is tropical monsoon, with a long rainy season, from April to September, with at least one heavy rain every day. Plains are flooded when water is encountered, and mountain construction is even more difficult.
Faced with many difficulties, the project department to carry out technical research. In view of the special geological conditions such as local paddy fields and swamps, the project department has invested 620 16mm thick steel plate pads to ensure the passage of equipment. There is a lot of rain in the local area, so the project department will take advantage of the rain to carry out construction. The local temperature is high, humid and sultry. The construction unit goes to the construction site at 4 o'clock every day, takes a rest at noon, avoids the high temperature period, and then works from 3 pm to 9 pm.
In the construction line, the reporter felt the bad construction environment. After a heavy rain, the temperature rose to 40 degrees Celsius. Employees in the wet work belt, even if standing still, work clothes will be soaked with sweat. After two hours of homework, employees can take off their rain boots and pour out water. Employees said it was sweat flowing down their bodies into their boots. In order to cope with high-temperature operations, the project department has equipped the unit with a large-capacity freezer to ensure that the unit employees can drink ice water and mung bean soup every day, and at the same time provide employees with heatstroke prevention and cooling drugs, and provide each employee with an additional set of work clothes for timely replacement.
It is under such difficult conditions that all the staff of the Nanning Branch Trunk Line Project Department of the Fifth Pipeline Company overcome difficulties and use the spirit of "ants gnawing bones" to make the project proceed smoothly.